6-1.
GENERAL Conformity and compliance inspections are required during
STC application projects. See the latest revision of FAA
Order 8100.4, Type Certification Process. 6-2. CONFORMITY
INSPECTIONS. a. Conformity inspections are required to verify that an
aircraft component or modification conforms to the data
submitted to the FAA, and that the product being
certificated complies with the Type design. These
inspections physically compare the component or modification
to the engineering specifications, drawings, and the
airworthiness standards. Conformity inspections are
instigated by filling out FAA Form 8110-1, Type Inspection
Authorization or FAA Form 8120-10, Request for Conformity,
and submitting it to the MIDO through the ACO project
engineer. Conformity inspections are recorded and reported
on FAA Form 8100-1, and FAA Form 8130-3 is completed if
required. See appendix 4 and the latest revision of FAA
Order 8110.4. NOTE: An FAA conformity inspection should be successfully
conducted before any official FAA tests (ground or flight)
are conducted. Conformity inspections are requested by FAA
engineering. b. Conformity Inspectors may either be Aviation Safety
Inspectors (Manufacturing), or FAA authorized Designated
Manufacturing Inspection Representatives (DMIR), and
manufac-turing DAR's. FAA manufacturing aviation safety
inspectors are located at various MIDO's throughout the
certifying directorate. c. FAA Form 8130-9, Statement of Conformity, ensures that
parts are manufactured and/or installed to the latest
revision of the descriptive data, prior to FAA inspection.
The applicant signifies this by signing FAA Form 8130-9 and
noting any deviations listed. In addition, for completed
products, the applicant is required to certify that the
modified aircraft, engine, or propeller is in conformity
with the original Type Design, except as affected by the
modification being presented for approval and by other
previ-ously approved modifications. d. Test articles are built in accordance with engineering
data. All components which are to be part of an initial STC
modification and require tests, other than flight tests,
(such as structural, fuel flow, etc.), require a complete
part conformity inspection before the test is started unless
prior authorization is obtained to allow a post test
conformity inspection. All modifications which require
flight testing must have a complete conformity inspection
via the TIA, be tagged (FAA Form 8130-3), and have a
satisfactory installation conformity before FAA ground or
flight tests can be conducted. See FAA Order 8110.4. e. Progressive inspections may be conducted by the
manufacturing aviation safety inspector at appropriate
intervals during the modification process if coordinated
early in the project. 6-3. COMPLIANCE
INSPECTIONS. These are required to verify that a particular component
or modification to an existing design meets the requirements
of the applicable 14 CFR's or CAR's through a combination of
specification review and physical inspection of the
component, installation, or aircraft. FAA engineering and
AEG personnel or an authorized DER arranges and conducts
these inspections. See the latest revision of FAA Order
8110.4. 6-4. PARTS MANUFACTURER APPROVAL (PMA)
AND PRODUCTION INSPECTIONS. If production parts are to be manufactured prior to
obtaining a "multiple" STC, control over all manufactured
"production" parts should be maintained by the applicant
until FAA approval of the STC and production. Production
parts produced prior to PMA approval should not be shipped.
Design changes may require additional certification testing.
The MIDO will only do conformity inspections on parts
required for ground or flight tests required to obtain STC
approval. They will not inspect production parts. See Order
8120.9 and Advisory Circular 21-32A. NOTE: MIDO/Manufacturing DAR's may inspect multiple ship
sets of parts, some used for the STC and some designated for
production, if the parts are required to be shipped to a
remote site where the test and production aircraft are being
modified. 6-5. TYPE INSPECTION
AUTHORIZATION. A TIA specifies installation conformity inspection and
certain ground and required flight tests to be performed by
the FAA or FAA designee. It also requires submittal of FAA
Form 8130-9 stating that the article has been inspected and
corresponds to the design data. The FAA inspector or
designee will then verify conformity. See 6-2.d. above and
chapter 7.
We
help Organizations quickly Conceptualize, Design, Develop,
and Implement Innovative Cost-Effective Solutions for
Avionics, Aircraft, and Flight Guidance-Navigation-Control
Systems.
![]()
![]()
![]()
![]()
![]()
Home
YOU
US
What
We Can
Do
What
We Have
Done
-
On
Learjets
![]()
Why
ASTECH
ASTECH's
Founder
Expert's
Corner
-
FAA STC Process
Links
In
Closing
CHAPTER 6. INSPECTIONS
6-2. CONFORMITY INSPECTIONS
6-3. COMPLIANCE INSPECTIONS
6-4. PARTS MANUFACTURER APPROVAL (PMA) AND PRODUCTION
INSPECTIONS
6-5. TYPE INSPECTION AUTHORIZATION
6-1. GENERAL.
For more information on how ASTECH Engineering may be able
to help you, please contact Jeff Wilson at astech@cox.net
or call 316-304-6157.
© Copyright 1996 ASTECH Engineering. All rights
reserved. No part of this document may be reproduced in any
form without the expressed written consent of the
author.
![]()
Keywords:
Concept Research Development Integration Integrated Aviation
Avionics Aircraft Flight Controls
Autopilots Navigation Guidance Analysis Simulation Software
Algorithms Hardware Interfaces
Requirements Engineers HITL FCS GPS FMS UAV
Systems