EXAMPLE STC CHECK SHEET

_____

Application from STC/Amendment or Drawing List approval (dated __________).

_____

Application Form 8110-12

_____

Certification Plan

_____

FAA letter of acknowledgment transmitted. #: ___________________ Date: __________

_____

Compliance Checklist

_____

Drawing review: Completed/DER Approved. Drawing: __________ Rev: __________

_____

Document List #: _______________________ Rev.: __________ Date: __________

_____

Report review: Completed /DER Approved. Report: ______________ Rev: __________

_____

Reports Submitted: ___________________________________________________________

_____

___________________ test plan/report acceptable. Number: ___________ Rev: __________

_____

___________________ systems data reviewed and accepted by: _______________________

_____

___________________ data reviewed and accepted by: ______________________________

_____

___________________ substantiation acceptable. Report:___________ Rev. __________

_____

___________________ test plan/report acceptable. Number: ___________ Rev: __________

_____

___________________ substantiation acceptable. Report:___________ Rev. __________

_____

___________________ test plan/report acceptable. Number: ___________ Rev: __________

_____

Weight and Balance supplement acceptable.

_____

Flight manual supplement reviewed and accepted by Flight Test Branch.

_____

TIA (if applicable) approved/transmitted.

_____

Flight test report complete and acceptable.

_____

DER Statement of Compliance Form(s) 8110-3 received.

_____

Instructions for Continued Airworthiness reviewed and accepted by AEG.

_____

Part conformity inspection requested. D/L: ________________ Rev: ___________

_____

Part conformity inspection acceptable.

_____

Installation conformity inspection requested. D/L: ___________ Rev: ___________

_____

Installation conformity inspection acceptable.

_____

STIR complete.

_____

Other requirement(s): ___________________________________________________

STC/Drawing List approval:

Signed: ____________________ STC #: _______________ Date: _______________

_____

Conformity Inspection Record(s) Form 8110-1 Received: ______________________

_____

Project closed out: (date _______________).

_____

Remarks:_____________________________________________________________

_____________________________________________________________________

_____________________________________________________________________


For more information on how ASTECH Engineering may be able to help you, please contact Jeff Wilson at astech@cox.net or call 316-304-6157.

© Copyright 1996 ASTECH Engineering. All rights reserved. No part of this document may be reproduced in any form without the expressed written consent of the author.

Keywords: Concept Research Development Integration Integrated Aviation Avionics Aircraft Flight Controls
Autopilots Navigation Guidance Analysis Simulation Software Algorithms Hardware Interfaces
Requirements Engineers HITL FCS GPS FMS UAV Systems